A punch list is the list of work that still has to be finished or fixed before a construction job is complete, made during a walkthrough near the end of the project. A good punch list template tracks an item number, location, description, responsible trade, priority, photo, due date, status, and sign-off for every item, and ends with a signed closeout section where the customer accepts the finished work. Walk it with the customer before the final payment, fix every item, then walk it again and sign.

Free template

Free construction punch list template

A landscape punch list with project details, a priority key, 28 numbered item rows (location, description, responsible party, priority, due date, photo, sign-off), notes, and customer closeout signatures.

What's included

  • Landscape layout with 28 numbered item rows
  • A/B/C priority key (safety, functional, cosmetic)
  • Responsible party, due date, photo #, and sign-off columns
  • Notes and completion sign-off with signatures
  • Excel version has priority and status dropdowns with open and closed counts
Download PDFFillable.pdf · 470 KB

No sign-up required. Free to use and edit for your business.

In Ardovia, your logo and company details go on every proposal, change order, and invoice automatically. See it in a demo

What is a punch list?

A punch list is a written list of the items that are unfinished, damaged, or not built to spec at the end of a job. Each item is something specific a crew can fix: a chipped coping stone, a missing outlet cover, grout that needs touching up.

The punch list is how a job gets closed out. The contractor works the list, the customer confirms each item is done, and both sides sign. That signature is what separates "the job is finished" from "the job is almost finished."

It is not a scope list or a wish list. New work the customer asks for during the walk is a change, not a punch item. Write it up as a change order so it is priced and signed.

Example

See it filled in

Here is the same template completed for a sample job, so you can see how much detail goes in each field before you fill out your own.

Sample data is fictionalDownload Fillable PDF (blank)
Construction punch list template, filled in for a sample job. Every name, address, and amount is fictional.

When should you walk a punch list?

Walk the punch list when the work is substantially complete — the job is usable, but the details are not all done. Walk too early and the list is just your remaining schedule. Walk too late and the customer finds the problems before you do.

  • Internal pre-punch: your superintendent walks the job alone first and fixes the obvious items. The customer should never be the one to find the paint on the tile.
  • Customer punch walk: walk the job with the customer, write every item down, number it, and agree on it on the spot.
  • Trade-specific punch: some trades get their own list as they finish, before the next trade covers their work.
  • Final walk: re-walk the list after the work is done. The customer checks each item off and signs.
  • Warranty or 30-day walk: some builders schedule a second walk after the customer has used the project for a few weeks. Items found later are warranty work.

Punch list template: the fields to include

Every field is there so a crew can find the item, fix it, and prove it is done without a phone call.

FieldWhat to enterWhy it matters
Item #A number for every item, in orderLets everyone refer to "item 7" instead of describing it again
Location / areaWhere the item is: room, wall, side of the pool, equipment padThe crew finds it without hunting
DescriptionWhat is wrong and what "fixed" looks like"Regrout 3 joints, top step" is fixable; "grout issue" is not
Trade / responsible partyThe crew, subcontractor, or person who owns the fixUnassigned items don't get done
PriorityA (safety/code), B (functional), C (cosmetic)Safety and code items get fixed first
PhotoA photo or photo number showing the itemSettles what the item was if it is disputed later
Due dateWhen the item should be completeKeeps the list from dragging past final payment
StatusOpen, in progress, done, or moved to warrantyShows how close the job is to closeout
Sign-offInitials of the person who verified the fixProof the item was checked, not just reported done

Example: a pool-build punch list (hypothetical)

Here is what a filled-in punch list looks like on a gunite pool after interior finish and startup. All names and items are examples.

#LocationItemResponsiblePriorityStatus
1Pool gateGate does not self-latch on every close — adjust hinge tensionFence subAOpen
2Equipment padValve handles not labeled (pool / spa / spillway)Service techBDone
3Equipment padPump lid weeping at o-ring — replace o-ring and re-checkService techBDone
4SpaSpa light not on the automation scheduleElectricianBOpen
5StepsGrout missing in 3 joints of waterline tile, top stepTile crewCOpen
6Coping, NE cornerChipped coping stone — replace one pieceCoping crewCOrdered
7DeckExpansion joint between coping and deck not sealed on the east sideDeck crewBOpen
8DeckPlaster overspray on pavers by the skimmer — cleanFinish crewCDone
9StartupCustomer orientation not done: equipment, brushing, chemistrySuperintendentBScheduled
10StartupAutomation app not connected to customer's phoneService techCOpen

Hypothetical example for illustration. Your items, trades, and priorities will differ by job.

Step by step

How to run a punch list from walk to sign-off

The template is the easy part. The process is what gets the job closed and the final payment collected.

  1. 1

    Pre-punch the job yourself

    Walk the job with the superintendent a few days before the customer does. Fix what you can and put the rest on the list. A short customer list builds trust; a long one starts an argument.

  2. 2

    Walk with the customer and write everything down

    Number each item, note the location, and take a photo. Agree on each item as you go. If the customer raises something that is not in the contract, say so on the spot and offer a change order.

  3. 3

    Assign every item and set due dates

    Give each item an owner and a due date. Group items by trade so one subcontractor visit clears several items. Safety and code items go first, especially anything an inspector will look at.

  4. 4

    Track status and verify each fix

    When a crew says an item is done, someone who did not do the work checks it and initials it. Take an "after" photo next to the "before" photo.

  5. 5

    Re-walk, sign, and close out

    Walk the list again with the customer. Each item gets checked off, and the customer signs the closeout section. Anything still open is written down with a date or moved to warranty in writing.

Closeout sign-off: what the customer is signing

The closeout section is short, but it matters. The customer confirms the items on the list were completed and reviewed with the contractor, and that any items still open are listed and will be handled under the warranty.

Tie the punch list to your payment terms. Many contracts make the final draw due at substantial completion or after the punch list is signed. Whichever you use, write it into the contract — see the payment schedule section of our construction proposal template — so the final walk does not turn into a negotiation over money.

Get every owner's signature, with a date. If two people signed the contract, both should sign the closeout.

Punch list best practices

A few habits keep punch lists short and closeouts clean.

  • One item per line. "Fix tile and coping" is two items with two crews.
  • Write the fix, not just the problem: "replace one coping stone, NE corner" beats "coping chipped."
  • Photograph every item when you find it and again when it is fixed.
  • Keep the list in one place. A list split across texts, emails, and a clipboard always misses something.
  • Do not let the punch list absorb new scope. New requests are change orders.
  • Set a target date for the whole list, not just each item, and tell the customer what it is.
  • Keep a daily log of punch work so you can show when each item was fixed.

Running punch lists in Ardovia

A paper punch list works for one job. Across many jobs, the items, photos, and signatures end up in different places. Software keeps them on the job.

In Ardovia, a punch list is part of a custom checklist — for example a final walkthrough template your team fills out on a phone or tablet at the job. Any field can require a photo, and signature and initial fields capture a signature on screen. The Punch List field collects outstanding items one by one, each with an optional assignee and due date. When the checklist is submitted, those items become a Punch List task with one sub-task per item, so each person sees what they own. A completed checklist produces a PDF that is emailed to the people you choose and can be sent to the customer.

For a formal closeout, a template can turn on the punch list workflow: the customer approves the list through an emailed link before work starts, a reviewer on your team checks the finished work and can reopen specific items, and the customer signs off at the end — in person on screen or by e-signature. Anything that comes up after closeout goes into a warranty claim on the same job. If you build pools, see how this fits with the rest of our pool builder software.

Checklists / Final Walkthrough

Bell Residence

1420 Lakeshore Dr, Austin, TX

Change
Pool surface free of defects?
YesNo
Water level (inches from tile)
4in
Equipment pad photoPhoto required
Homeowner sign-off
Save DraftComplete

Free template

Free construction punch list template

Download PDFFillable.pdf · 470 KB

No sign-up required. Free to use and edit for your business.

Built for contractors

Run your contracting business in one place

Ardovia handles leads, proposals, change orders, scheduling, permits, and job costing for pool builders and contractors.

Book a Demo

Frequently asked questions

What is a punch list in construction?

A punch list is a list of work that is unfinished, damaged, or not built to the contract at the end of a construction project. It is created during a walkthrough near substantial completion, each item is fixed and verified, and the customer signs off when the list is complete.

What should a construction punch list template include?

A construction punch list template should include project details, a numbered list of items with the location, a description of the fix, the trade or person responsible, a priority, a photo reference, a due date, a status, and initials when the fix is verified, followed by a closeout section where the customer and contractor sign and date.

When should a punch list be done?

A punch list should be done when the job is substantially complete — usable, but with details still to finish. Most contractors walk the job internally first, then walk it with the customer, fix the items, and re-walk the list for a final sign-off before or alongside the final payment.

Who is responsible for completing punch list items?

The contractor is responsible for making sure every punch list item is completed, but each item should be assigned to the specific crew, subcontractor, or person who will fix it. Assigning an owner and a due date to every item is what keeps the list from stalling.

Is a punch list the same as a change order?

No. A punch list covers work that is already in the contract but is unfinished or not done right, so it has no extra cost. New work the customer asks for during the walkthrough is a change in scope and should be written up and signed as a change order before it is done.

What happens to punch list items found after closeout?

Items found after the customer signs the closeout are normally handled as warranty work under the terms of the contract. Record each one as a warranty claim with photos and a description, so it is tracked to completion like any other job.